The project's architect presented a preliminary cost breakdown for the proposed Marietta High School auditorium totaling the project from half a million to several million dollars over budget.

Preliminary estimates show auditorium coming in over budget from between half a million to several million dollars, The Marietta Daily Journal reports.

The project’s architect, Bob Sussenbach of CGLS of Atlanta, presented a preliminary cost breakdown of the theater calculated by , totaling the project at $9.5 million, the MDJ says.

' plan was to build a multipurpose auditorium at for an estimated $9 million. The to pay for the new auditorium.

Find out what's happening in Mariettawith free, real-time updates from Patch.

The in a 2013 referendum, as the sales tax revenue will be used pay off the auditorium debt.

The bond will be placed on next year’s presidential primary election ballot. If city voters approve the five-year bond, construction should be done sometime in 2013.

Find out what's happening in Mariettawith free, real-time updates from Patch.

If the 2012 bond passes but SPLOST IV fails, owners of homes valued at $200,000 will face a tax increase of about $11 a year to pay off the bond, starting in 2015.

Rejecting the 2012 bond would delay the project until the 2013 SPLOST IV vote. A yes at that point would allow construction to begin in 2014; a no vote would shelf the project indefinitely.